One man - SOOO many boards |
Photo of center wall. The ceiling in the living area is a cathedral ceiling. The wall up to 10' was built in sections and lifted up and bolted down and to the adjoining sections and floor. Above 10' is a work in progress. An opening on the left will remain there until the A/C and plywood attic flooring is completed.
The last two days we have focused on our 24' foot exposed I beam in the center of the living area and preparing it for rafters. First we attached a 2' x 10' to the top and bottom of the metal beam. These 2 bys will make installing the 40 rafters easier and more stable. Then we added two metal straps for just a little extra support. The straps will not be visible once the ceiling boards are installed. Finally, we added 24" wide plywood on both sides of the beam. Our final vision is for the beam to be finished off with a nice finishing wood. It is way up there!